Santa Paula High School Baseball Field Fencing Project
Bids for a project that included both field lights and fencing modifications were rejected in December 2024. Thereafter, this project was "re-scoped" to eliminate the field lighting and only include fencing improvements; DSA approval was received in September 2025 for the re-scoped bid documents. The fencing improvements will include new, permanent left-field fencing and new 20' high right-field fencing adjoining the westernmost four tennis courts.
Six bids were received for the construction contract on October 28, 2025, and the contract was awarded on November 12, 2025.
Construction is scheduled to follow the 2026 baseball season during the summer of 2026.