Isbell Modernization Project
HMC Architects lead SPUSD through the programming phase for the modernization of the existing two-story building, as the building has seismic issues that need to be rectified. Programming efforts included public outreach (both surveys and public meetings) and gathering input from all District stakeholders, including students, parents of students, site staff, and District personnel. Concurrent to the programming phase, the District carried out the CEQA process to address the historical resources aspect of the building. A final EIR was certified by the Board of Trustees on March 26, 2025.
Ultimately, HMC Architects was selected to carry out this project's design. Schematic design is complete, and design development is currently in progress.
The District has also started the solicitation process for the lease/leaseback contracting method. The District aims to retain a general contractor during the design phase to assist with the project design, constructability, and cost estimating; a pre-construction services contract is slated for board approval on 6/25/25.